What happens if a developer in Peru is late delivering your home?
If the developer misses the agreed delivery date, you can demand delivery plus any late-delivery penalty in your contract, without proving what you lost. You can also terminate the contract and claim damages. As a general rule, you first have to demand performance in writing to put the developer in default.
VerificationVerified against the official sourceSee the sources ↓
- 14sources cited
- 14read at the official source
- 1official institutions
Peruvian State portal (gob.pe)
Checked 1 Oct 2026Next review 30 Mar 2027
The delivery date comes from your contract
The Civil Code has a default rule for sales. Article 1552 says:
“El bien debe ser entregado inmediatamente después de celebrado el contrato, salvo la demora resultante de su naturaleza o de pacto distinto.”
(The property must be handed over right after the contract is signed, unless a delay follows from its nature or the parties agreed otherwise.)
When you buy off-plan, the home does not exist yet, so the contract sets the date. If you buy from a developer, Law 29571 (the Consumer Protection Code) requires that date in writing. Article 78.1 lists the minimum content of the contract, including:
“g. Plazo, fecha o condiciones expresas de entrega del inmueble y penalidades por incumplimiento que se hubieran pactado. h. Supuestos en los cuales se aplican penalidades y el monto de las mismas.”
(The term, date or express conditions of delivery, the penalties agreed for breach, when those penalties apply and how much they are.)
So start with your contract. It holds the delivery date or term, any conditions it depends on, and the penalty for being late. Everything else on this page depends on what it says.
When the developer is in default (mora)
A missed date is not always enough. Article 1333 of the Civil Code sets the rule:
“Incurre en mora el obligado desde que el acreedor le exija, judicial o extrajudicialmente, el cumplimiento de su obligación.”
(The obligor is in default from the moment the creditor demands performance, in or out of court.)
The same article lists four exceptions where no demand is needed. Two matter here: when the contract expressly says no demand is needed, and when the delivery date “hubiese sido motivo determinante” (was a decisive reason) for signing. If your contract says nothing, do not count on a judge treating your date as decisive. Demand delivery in writing. A notarial letter (carta notarial) gives you proof of the date the developer received it.
Default has a concrete effect. Article 1336 says a party in default “responde de los daños y perjuicios que irrogue por el retraso en el cumplimiento de la obligación” (is liable for the damage caused by the delay). The developer can escape that if it proves the delay was not its fault. That proof is on the developer.
The late-delivery penalty (cláusula penal)
Many contracts set a penalty per day or month of delay. Four rules matter.
You don’t have to prove damage. Article 1343 says:
“Para exigir la pena no es necesario que el acreedor pruebe los daños y perjuicios sufridos. Sin embargo, ella sólo puede exigirse cuando el incumplimiento obedece a causa imputable al deudor, salvo pacto en contrario.”
(You don’t need to prove damages to claim the penalty. But it can only be claimed when the breach is due to a cause attributable to the debtor, unless the contract says otherwise.)
You can collect it and still demand the home. If the penalty was agreed for late performance, article 1342 lets you demand “además de la penalidad, el cumplimiento de la obligación” (performance in addition to the penalty).
The penalty is usually the cap. Article 1341 says the penalty limits compensation to that amount, “salvo que se haya estipulado la indemnización del daño ulterior” (unless compensation for further damage was agreed). If your contract says nothing about further damage, you cannot recover more than the penalty, even if your costs are higher.
A judge can reduce it. Article 1346 lets a judge, at the debtor’s request, reduce the penalty “cuando sea manifiestamente excesiva” (when it is clearly excessive). If your penalty is high, the developer can ask for it to be cut.
No penalty in the contract: damages
If your contract has no penalty, you can claim the damage the delay causes you. Article 1321 says compensation for “tardío” (late) performance covers “tanto el daño emergente como el lucro cesante, en cuanto sean consecuencia inmediata y directa de tal inejecución” (both direct loss and lost profit, as far as they are an immediate and direct consequence). If the delay is due to slight negligence (culpa leve), compensation is limited to damage that was foreseeable when the contract was signed.
Rent you pay while you wait is the obvious example of direct loss. That is our reading, not the wording of the law. Keep leases and receipts: without proof of damage there is no compensation.
Terminating the contract (resolución)
If you no longer want to wait, you can get out. Article 1428 says that when one party fails to perform, the other “puede solicitar el cumplimiento o la resolución del contrato y, en uno u otro caso, la indemnización de daños y perjuicios” (can ask for performance or termination and, either way, damages).
You have three routes:
| Route | What the law says |
|---|---|
| Lawsuit for termination | Once the developer is served with the termination claim, it can no longer perform (article 1428). |
| Notarial letter with a deadline | You give “no menor de quince días” (no less than fifteen days) to deliver, warning that otherwise the contract is terminated. If it does not deliver, the contract “se resuelve de pleno derecho” (is terminated by operation of law) and the developer owes damages (article 1429). |
| Express termination clause | If your contract says it terminates if delivery is not made on a precise date, termination happens when you tell the developer you are invoking that clause (article 1430). |
Think before you terminate: it means giving up the home. What happens to the money you paid is covered in what happens to your money if a real estate project falls through. If you paid arras, also read how arras work.
Late delivery as a consumer problem
If you buy from a developer, Law 29571 applies alongside the Civil Code. Article 18 defines suitability (idoneidad) as “la correspondencia entre lo que un consumidor espera y lo que efectivamente recibe, en función a lo que se le hubiera ofrecido” (the match between what a consumer expects and what they actually receive, based on what was offered), and article 19 says “el proveedor responde por la idoneidad y calidad de los productos y servicios ofrecidos” (the supplier answers for the suitability and quality of what it offers). Handing over the home after the date offered can be raised with Indecopi as a lack of suitability.
We don’t repeat the complaint channels here. They are in buying a home in Peru: what to check before you sign, in the section “Where to complain if something doesn’t match”. If your contract’s penalty only punishes the buyer, also read adhesion contracts and unfair terms.
What this page does not cover
We did not review Indecopi decisions or court rulings on late delivery of homes, or how compensation is calculated in practice. We do not cover limitation periods for civil claims, or purchases made with the Techo Propio housing bonus (Bono Familiar Habitacional) or a Mivivienda loan. We also do not cover the handover record (acta de entrega) or defects that show up later.
How to file
- Read your contractLook for four things: the delivery date or term and its conditions, the late-delivery penalty and when it applies, whether compensation for further damage (daño ulterior) was agreed, and whether there is an express termination clause (cláusula resolutoria).
- Demand delivery in writingSend the developer a written demand for delivery. As a general rule, that demand puts it in default (article 1333). A notarial letter (carta notarial) gives you proof of the date it was received.
- Keep proof of what the delay costs youLease contracts and rent receipts, rescheduled moves, instalments paid. You need them if you claim damages beyond the penalty, or if there is no penalty.
- Decide: wait with the penalty, or terminateYou can demand delivery plus the late-delivery penalty (article 1342). If you want out, you can send a notarial letter giving at least fifteen days to deliver, warning that otherwise the contract is terminated (article 1429), or invoke the termination clause if your contract has one (article 1430).
- If the developer ignores you, file a complaintThe complaint channels against a developer are explained in our general guide to buying a home, in the section 'Where to complain if something doesn't match'.
What people fail to ask in time
And if they finally hand over the home, but with defects you can't see at first?
Find out before it matters →What most people believe — and what the law says
As soon as the delivery date passes, the developer is in default.
The general rule in article 1333 of the Civil Code is that default starts when you demand performance, in or out of court. There are exceptions, for example when the contract expressly says no demand is needed. Read your contract and, if in doubt, demand delivery in writing.
To collect the late-delivery penalty I have to prove how much I lost.
No. Article 1343 says you do not need to prove damages to claim the penalty. It does require that the delay be due to a cause attributable to the developer, unless the contract says otherwise.
If I collect the penalty, I give up my right to the apartment.
When the penalty was agreed for late performance, article 1342 lets you claim the penalty and also demand delivery.
If the developer is late, the contract is automatically void.
The contract does not undo itself. Article 1428 lets you choose between demanding performance and terminating. To terminate you need a lawsuit, a notarial letter giving a deadline (article 1429), or an express termination clause that you choose to invoke (article 1430).
Frequently asked questions
My contract says delivery is 'approximate' or depends on the municipal sign-off. Can I still complain?
Law 29571 requires the contract to state the term, date or express conditions of delivery (article 78.1, item g). If the date depends on a condition, that condition has to be written down. Read exactly what your contract says: that decides when the delay starts. If the clause is unclear, you can raise it as a lack of suitability (idoneidad) in a complaint.
I'm paying rent because the unit isn't ready. Can I get that back?
Article 1336 makes a party in default liable for the damage the delay causes, and article 1321 covers direct losses and lost profits that are an immediate and direct consequence. That rent falls under this is our reading. There is a limit: if your contract has a penalty, article 1341 caps compensation at that penalty, unless the contract also provides for compensation of further damage (daño ulterior).
The developer blames the municipality for the delay. Is it off the hook?
It can escape liability if it proves the delay was not its fault (article 1336). And the penalty can only be claimed when the breach is due to a cause attributable to the developer, unless the contract says otherwise (article 1343). Ask for the cause and the permit dates in writing; proving it is the developer's job.
The penalty in my contract is tiny. Can I ask for more?
Only if the contract provides for compensation of further damage. Then the developer pays the full penalty and, if your losses were larger, the penalty counts toward them (article 1341). Without that clause, the penalty is the cap.
If I terminate, do I get my money back?
Article 1428 lets you ask for termination plus damages. How you recover your payments when the sale falls through because of the developer is covered on our page about what happens to your money if a project falls through.
The exact law
Código Civil (Decreto Legislativo N.º 295)Artículo 1552read
When a sold property must be handed over
«El bien debe ser entregado inmediatamente después de celebrado el contrato, salvo la demora resultante de su naturaleza o de pacto distinto.»
Ley N.º 29571, Código de Protección y Defensa del ConsumidorArtículo 78, numeral 78.1, literales g) y h)read
The contract must state the delivery term and the penalties
«g. Plazo, fecha o condiciones expresas de entrega del inmueble y penalidades por incumplimiento que se hubieran pactado. h. Supuestos en los cuales se aplican penalidades y el monto de las mismas.»
Código Civil (Decreto Legislativo N.º 295)Artículo 1333read
When the obligor is in default
«Incurre en mora el obligado desde que el acreedor le exija, judicial o extrajudicialmente, el cumplimiento de su obligación. No es necesaria la intimación para que la mora exista: 1.- Cuando la ley o el pacto lo declaren expresamente. 2.- Cuando de la naturaleza y circunstancias de la obligación resultare que la designación del tiempo en que había de entregarse el bien, o practicarse el servicio, hubiese sido motivo determinante para contraerla. 3.- Cuando el deudor manifieste por escrito su negativa a cumplir la obligación. 4.- Cuando la intimación no fuese posible por causa imputable al deudor.»
↳Artículo 1336read
A party in default is liable for damage caused by the delay
«El deudor constituido en mora responde de los daños y perjuicios que irrogue por el retraso en el cumplimiento de la obligación y por la imposibilidad sobreviniente, aun cuando ella obedezca a causa que no le sea imputable. Puede sustraerse a esta responsabilidad probando que ha incurrido en retraso sin culpa, o que la causa no imputable habría afectado la prestación aunque se hubiese cumplido oportunamente.»
↳Artículo 1321read
What compensation for late performance covers
«El resarcimiento por la inejecución de la obligación o por su cumplimiento parcial, tardío o defectuoso, comprende tanto el daño emergente como el lucro cesante, en cuanto sean consecuencia inmediata y directa de tal inejecución. Si la inejecución o el cumplimiento parcial, tardío o defectuoso de la obligación, obedecieran a culpa leve, el resarcimiento se limita al daño que podía preverse al tiempo en que ella fue contraída.»
↳Artículo 1341read
A penalty caps compensation unless further damage was agreed
«El pacto por el que se acuerda que, en caso de incumplimiento, uno de los contratantes queda obligado al pago de una penalidad, tiene el efecto de limitar el resarcimiento a esta prestación y a que se devuelva la contraprestación, si la hubiere; salvo que se haya estipulado la indemnización del daño ulterior. En este último caso, el deudor deberá pagar el íntegro de la penalidad, pero ésta se computa como parte de los daños y perjuicios si fueran mayores.»
↳Artículo 1342read
A late-performance penalty can be claimed on top of delivery
«Cuando la cláusula penal se estipula para el caso de mora o en seguridad de un pacto determinado, el acreedor tiene derecho para exigir, además de la penalidad, el cumplimiento de la obligación.»
↳Artículo 1343read
No proof of damage is needed to claim the penalty
«Para exigir la pena no es necesario que el acreedor pruebe los daños y perjuicios sufridos. Sin embargo, ella sólo puede exigirse cuando el incumplimiento obedece a causa imputable al deudor, salvo pacto en contrario.»
↳Artículo 1346read
A judge can reduce a clearly excessive penalty
«El juez, a solicitud del deudor, puede reducir equitativamente la pena cuando sea manifiestamente excesiva o cuando la obligación principal hubiese sido en parte o irregularmente cumplida.»
↳Artículo 1428read
On breach: demand performance or terminate, plus damages
«En los contratos con prestaciones recíprocas, cuando alguna de las partes falta al cumplimiento de su prestación, la otra parte puede solicitar el cumplimiento o la resolución del contrato y, en uno u otro caso, la indemnización de daños y perjuicios. A partir de la fecha de la citación con la demanda de resolución, la parte demandada queda impedida de cumplir su prestación.»
↳Artículo 1429read
Termination by notarial letter giving at least fifteen days
«En el caso del Artículo 1428º la parte que se perjudica con el incumplimiento de la otra puede requerirla mediante carta por vía notarial para que satisfaga su prestación, dentro de un plazo no menor de quince días, bajo apercibimiento de que, en caso contrario, el contrato queda resuelto. Si la prestación no se cumple dentro del plazo señalado, el contrato se resuelve de pleno derecho, quedando a cargo del deudor la indemnización de daños y perjuicios.»
↳Artículo 1430read
Express termination clause
«Puede convenirse expresamente que el contrato se resuelva cuando una de las partes no cumple determinada prestación a su cargo, establecida con toda precisión. La resolución se produce de pleno derecho cuando la parte interesada comunica a la otra que quiere valerse de la cláusula resolutoria.»
Ley N.º 29571, Código de Protección y Defensa del ConsumidorArtículo 18read
Suitability: what you expect versus what you get
«Se entiende por idoneidad la correspondencia entre lo que un consumidor espera y lo que efectivamente recibe, en función a lo que se le hubiera ofrecido, la publicidad e información transmitida, las condiciones y circunstancias de la transacción, las características y naturaleza del producto o servicio, el precio, entre otros factores, atendiendo a las circunstancias del caso.»
↳Artículo 19read
The supplier answers for suitability
«El proveedor responde por la idoneidad y calidad de los productos y servicios ofrecidos»
Also searched as: developer in peru did not deliver apartment on time · late delivery penalty apartment peru · can i cancel my off-plan purchase in peru if delivery is late · construction company delayed handover peru what to do · can the developer pay my rent while i wait for my apartment peru · notarial letter to developer for late delivery
Related
Buying a home in Peru: what to check before you sign, pre-construction or already built
Buying from a developer isn't the same as buying from an individual — the law gives you information rights and a 10-year warranty.
HousingWhat happens to your money if a real estate project in Peru falls through?
If the project falls through because of the seller, you're owed a full refund just by asking — no need to prove any harm.
HousingBuying a home in Peru: how arras (earnest money) work and when you actually own it
You become a homeowner in Peru when you sign the contract, not when you register it — and earnest money rules vary by type.
ConsumerAdhesion contracts and unfair terms in Peru: do I have to comply with everything I signed?
Accepting a contract does not bind you to everything in it. The law lists clauses that fail even if you sign.
ConsumerHow do you file a complaint with Indecopi? Reclamo vs. denuncia, step by step
You are taking this to Indecopi — which of the two routes fits, and how to file.
HousingOff-plan purchase contract in Peru: which clauses should you check before signing?
One clause about 'risk' can make you pay for an apartment that was never built. Do you know where to look for it?
HousingHome handover certificate in Peru: what to check before signing "conforme"
Signing "conforme" at handover does not erase your rights, but it can cost you the evidence.
HousingWhat happens if you stop paying installments on an off-plan home in Peru?
Falling behind does not mean losing everything you paid. The Civil Code says what the developer must give back.
What this page already lets you do
- Name the rule that protects you
- Copy the exact article and send it
- Follow the steps, in order